In short
The Electric Reliability Council of Texas, or ERCOT, manages the grid that serves about 90 percent of the state. ERCOT.com. Under PURA § 37.0561, a large load customer is an entity requesting a new or expanded interconnection where the total load at a single site exceeds a demand threshold of 75 megawatts, though the Public Utility Commission may set a lower threshold if necessary. PURA § 37.0561, ERCOT NPRR1234 overview, PURA § 37.0561, ERCOT Large Load Q&A. In 2025, Texas enacted Senate Bill 6, which gave the Public Utility Commission of Texas, known as the PUCT, authority to write new interconnection rules for large loads, including AI data centers. The queue of large loads waiting to connect to the grid has grown from 63 gigawatts in December 2024 to 410 gigawatts by March 2026, with roughly 87 percent of that from AI data centers. ERCOT Dec. 2025 Board Report, ERCOT December 2025 CDR, ERCOT April 2026 Update. The PUCT has proposed a rule that would require a developer to post $50,000 per megawatt of requested peak demand as financial security. Transmission-voltage customers that interconnect after December 31, 2025 must accept a protocol allowing their load to be curtailed during firm load shed events, unless the load is operated by a critical load industrial customer or designated as a critical natural gas facility. S.B. 6.
What is ERCOT and what counts as a large load?
ERCOT is an independent, nonprofit grid operator. It controls the flow of electricity to about 90 percent of the state’s electric load. ERCOT.com. Texas chose a competitive wholesale electricity market with no capacity market. That means generators earn money only when they sell energy, not simply for being ready. The market uses scarcity pricing with a $5,000 per megawatt hour price cap. When supply gets tight, wholesale prices can spike rapidly to encourage more generation. This market design requires that new large loads, like AI data centers, be integrated carefully to keep the grid reliable.
A large load under Texas law is one or more facilities at a single site whose combined peak demand reaches 75 megawatts or more. The aggregate peak demand is measured behind one or more common points of interconnection or service delivery points. ERCOT Large Load Q&A. The same 75 MW threshold appears in the Texas Public Utility Regulatory Act, section 37.0561. The PUCT can lower the threshold if needed. PURA § 37.0561 / S.B. 6. For example, the Stargate Abilene AI data center campus is built to draw 1.2 gigawatts, sixteen times the threshold. Epoch AI, Tax alert. A separate PUCT rule, 16 TAC § 25.370, uses a lower 10 MW threshold for load forecasting. That forecasting rule took effect on March 1, 2026 and helps ERCOT predict future demand, but the interconnection process itself stays with the 75 MW test. ERCOT April 2026 Update
What new rules did Senate Bill 6 put in place?
The Texas Legislature passed Senate Bill 6 on May 29, 2025. Governor Greg Abbott signed it on June 20, 2025, and it took effect immediately. Texas Legislature Online. The law directed the PUCT to overhaul how large loads connect to the ERCOT grid. It added several new sections to the Public Utility Regulatory Act.
The PUCT opened five rulemaking projects to carry out the law. The main one, Project 58481, is developing the interconnection standards for large loads. Other projects cover net metering and co location (58479), load forecasting (58480), reliability and demand reductions (58482), and transmission cost allocation (58484). Tax alert
The key mandates from S.B. 6 include
- Mandatory interconnection standards. The PUCT must write rules that set out a clear, enforceable process for connecting large loads to the grid. (PURA § 37.0561)
- Mandatory curtailment. Any large load that connects on or after January 1, 2026 must be ready to reduce its consumption when ordered by ERCOT. (PURA § 39.170)
- Net-metering review. A new large load that wants to share power behind the meter with an existing generator must go through an ERCOT study and get PUCT approval. (PURA § 39.169)
- Cost recovery for utilities. The transmission service provider, or TSP, that builds the interconnection can recover its costs through established rate mechanisms. (PURA § 35.004)
The PUCT must complete its transmission cost allocation rules by December 31, 2026, while other SB 6 rulemakings are on various timelines with final adoptions planned throughout 2026. Tax alert The PUCT published the proposed main interconnection rule, 16 TAC § 25.194, on March 12, 2026. The public comment period closed on April 17, 2026, and the final rule could be adopted as early as April 26, 2026. Texas Register Until the final rule is adopted, an interim process still applies.
How does an AI data center get connected to the ERCOT grid?
The process is governed by two frameworks. One is the ERCOT Planning Guide Section 9, adopted by the PUCT in May 2025 and effective December 15, 2025. ERCOT Large Load Q&A The other is the proposed PUCT rule 16 TAC § 25.194. Proposed 16 TAC § 25.194 These two are designed to work together and replace a temporary process that ERCOT had operated since March 2022. The old process was built for 40 to 50 large loads. Utility Dive The new process must handle hundreds.
Here are the steps.
Step 1. Notice and initial screening
The developer of the AI data center, called the large load customer, sends a notice to the interconnecting transmission service provider and to ERCOT. ERCOT screens the request. The developer also pays a minimum study fee of $100,000 for the initial transmission screening. S.B. 6
Step 2. Intermediate agreement and financial security
Before the detailed study can start, the developer must sign an Intermediate Agreement with the transmission service provider. Under the proposed PUCT rule, that agreement requires
- Proof of site control. A deed, a lease of five years or longer, or an option to purchase or lease.
- A disclosure of any substantially similar interconnection request the developer is pursuing, the approval of which would result in materially changing, delaying, or withdrawing this one. Proposed § 25.194, Proposed § 25.194
- A phased energization schedule.
- Financial security equal to $50,000 per megawatt of the requested peak demand. For a 1 GW project, that is $50 million. Proposed § 25.194
- A study fee. The fee is not less than $100,000 for loads of at least 75 MW and less than 250 MW, and not less than $300,000 for loads of 250 MW or more. The developer also must pay any actual study costs that go above those amounts. Proposed § 25.194
Step 3. Large Load Interconnection Study
The transmission service provider runs a Large Load Interconnection Study, or LLIS. The study covers steady-state analysis, short-circuit analysis, and dynamic and transient stability analysis. It mirrors the Full Interconnection Study that generators receive. The developer pays a $14,000 fee for each LLIS request. ERCOT Large Load Q&A, EPE Consulting
The developer has 180 days from the time the study notice is issued to meet a set of requirements in the Planning Guide. If the developer does not meet that deadline, the transmission service provider must issue a 30-day status update. If the developer fails to meet the 180-day deadline, ERCOT may notify the TSP that the project is subject to cancellation. If the TSP does not provide a status update within 30 days, ERCOT may consider the project cancelled. ERCOT Large Load Q&A
Step 4. Interconnection agreement and non refundable fee
Within 30 days after the study is finished, the developer must sign an Interconnection Agreement. That agreement requires
- A non-refundable interconnection fee of $50,000 per MW of contracted peak demand. Another $50 million for a 1 GW project. Proposed § 25.194
- Payment of 100 percent of the contributions in aid of construction, often called CIAC. This covers the direct costs the transmission service provider incurs to physically connect the AI data center to the grid.
- Additional security to cover the cost of system upgrades.
Step 5. Quarterly Stability Assessment and energization
Before the AI data center can receive power, it must complete the requirements of the ERCOT Quarterly Stability Assessment (QSA). ERCOT Large Load Q&A ERCOT also requires a voltage ride through evaluation. ERCOT proposes that large power electronic based loads such as AI data centers use constant-current control, with IEEE 1668 as a standard under consideration for voltage ride through, and it conducts an interim ride through assessment as a condition for energization. ERCOT VRT proposal, ERCOT Market Notice
Step 6. Forfeiture and refund of the security
If the developer withdraws the project or misses a milestone by more than six months, the security is split. 80 percent of the remaining security is applied to the transmission service provider’s rate base, which benefits all customers. 20 percent is refunded to the developer.
If the project reaches energization, 20 percent of the remaining security is refunded at certain milestones. Under the proposed rule, 20% of the remaining balance is refunded when the large load customer energizes, then ratably as it meets phased energization milestones, and any remaining balance is refunded after it sustains operations at the contracted peak demand for five years. Proposed § 25.194
How do curtailment and grid emergency rules affect AI data centers?
Any AI data center that interconnects after December 31, 2025 must be capable of mandatory curtailment. The transmission service provider, cooperative, or municipal utility must install equipment that lets ERCOT remotely reduce the facility’s load during a firm load shed event. Critical load industrial customers and critical natural gas facilities are exempt. S.B. 6, Tax alert
ERCOT also gained new emergency authority. If a large load facility has non exporting backup generation that can serve 50 percent or more of its on site demand, ERCOT may direct it to reduce its net consumption or run the backup generators. ERCOT can use this power only during or before a grid emergency, and only after it has exhausted all market services except frequency response. PURA § 37.0561 / S.B. 6
Separately, ERCOT must develop a voluntary demand reduction service. Under this service, ERCOT would pay large loads of 75 MW or more to reduce their consumption with at least 24 hours of notice. The program is meant to be used in anticipation of emergency conditions. Large load customers that curtail in response to wholesale electricity prices are prohibited from participating in the reliability service. PURA § 39.170(b) / S.B. 6
In practice, a large AI data center with on-site backup generators must be designed so that it can island itself from the grid and run on backup power when ERCOT orders it to do so. This has a direct impact on engineering, fuel supply contracts, and operating procedures.
What if the AI data center is co located with an existing power plant?
Senate Bill 6 added a review process for any new net-metering arrangement between a new large load (75 MW or more) and an existing stand alone generation resource. The existing generator must have been registered with ERCOT as a stand alone generation resource as of September 1, 2025. PURA § 39.169 / S.B. 6
The process works in two steps. First, ERCOT must complete a study within 120 days. Then the PUCT has 60 days after receiving the study results to approve, deny, or impose reasonable conditions on the arrangement. S.B. 6
There are two exemptions. The generator was majority-owned by the large load customer’s parent company as of January 1, 2025. Or the generator’s original ERCOT registration already listed a co located large load at the time it was first energized. S.B. 6
This provision prevents an AI data center from sidestepping the full interconnection review by simply striking a behind the meter power deal with an existing solar farm or gas plant that was not built for that purpose.
How big is the interconnection queue, and how much of it is real?
The queue has grown far faster than anything ERCOT expected.
| Date | Total large load queue (GW) | Share from AI data centers | Notes |
|---|---|---|---|
| Dec. 2024 | 63 GW | n/a | |
| Nov. 18, 2025 | 226 GW | ~73% | 225 new requests in 2025, more than the 152 filed in all of 2022-2024 combined. |
| Mar. 26, 2026 | 410 GW | ~87% | Average request size 725 MW in 2025, many over 1 GW. |
ERCOT Dec. 2025 Board Report, ERCOT April 2026 Update, Dave Friedman Substack
As of November 2025, only about 2 percent of the queue (5,302 MW) had actually been energized. ERCOT Large Load Q&A. Many industry observers are skeptical that most of these projects will ever be built. Former ERCOT Independent Market Monitor Beth Garza and UT Austin research scientist Joshua Rhodes have both questioned the physical feasibility of the queue. CNBC
To manage the volume, ERCOT is developing a batch study process. Batch Zero revision requests were filed on March 4, 2026, and the target effective date for the protocols is August 1, 2026. The batch process would group qualified large loads into a single study every six months and reserve capacity to avoid constant restudies. ERCOT April 2026 Update
The real world is already delivering projects. The Stargate Abilene site, for example, reached about 0.3 GW operating as of April 2026, with a full 1.2 GW expected by the end of 2026. Epoch AI But hundreds of other projects remain only in the queue.
Is Texas building enough generation and transmission to support all these loads?
The short answer is no, not yet. But the buildout is massive.
ERCOT’s all-time peak demand is 85.5 GW, set in August 2023. Total available generation capacity is about 105 GW. The queue for new generation interconnections is also enormous, roughly 432,000 MW to 453,000 MW. That breaks down into 178,000 MW of energy storage, 163,000 MW of solar, 61,000 MW of gas, and 48,000 MW of wind. ERCOT April 2026 Update Between 2024 and 2025, about 23 GW of new generation was synchronized to the ERCOT grid, with another 9.9 GW expected in the first half of 2026. ERCOT Dec. 2025 Board Report
The Texas Energy Fund, or TEF, is a $10 billion state loan and grant program that offers low interest loans to build dispatchable generation inside ERCOT. As of April 10, 2026, six projects had finalized loans totaling 3,564 MW and $2.65 billion. PUCT TEF page One of those is a 1,350 MW gas plant by Competitive Power Ventures that received a $1.12 billion loan at 3 percent interest. Latitude Media However, many TEF projects have withdrawn or asked for extensions into 2026 and 2027, citing turbine procurement delays and thin market forwards. Latitude Media
On the transmission side, ERCOT endorsed the TX 765-kV STEP, a $32.99 billion plan for new high voltage lines. The first line, Oncor’s Longshore Switch to Drill Hole Switch line, is approximately 180 miles and is targeted for energization by December 2028. Oncor Newsroom A second line, the Bell County East Switch to Big Hill Substation line, runs 214 to 244 miles and is expected in service by summer 2030. Together these lines will move power from resource rich regions to load centers. ERCOT The 765-kV plan reduces the need to upgrade existing infrastructure by about 1,400 miles and is expected to save consumers $230 million more per year than the 345-kV alternative. ERCOT Trending Topics
Meanwhile, new gas fired generation is being built specifically for AI data centers. About 58 GW of gas projects were added to the Texas pipeline in 2025, nearly half of all upcoming Texas gas projects, totalling 40 GW, are planned to supply AI data centers directly. Texas Tribune Real projects include Pacifico Energy’s 7.65 GW complex in Pecos County, Fermi America’s 6 GW project near Amarillo, and Chevron’s first-ever power plant at 5 GW in West Texas. Texas Tribune
How long does the interconnection process take?
The entire process, from the initial notice to first energization, can take a year and a half or more. ERCOT’s published interconnection process runs 18 to 30 months for large generation and 8 to 12 months for small generation, not counting construction and supply delays, and a large load interconnection runs on a comparable timeline. ERCOT interconnection process The current queue backlog and supply chain constraints for transformers and switchgear are likely to push those timelines out. In the expected batch process, a project that misses a batch window could wait another six months for the next one.
A developer should plan for interconnection timelines to run parallel with site development, and to secure long dated equipment orders early.
Key takeaways
- Budget for significant upfront costs. A 1 GW AI data center faces $50 million in intermediate financial security, a $300,000 study fee, a $50 million non-refundable interconnection fee, and 100 percent of the direct construction costs. The total outlay before energization can exceed $200 million.
- Lock in site control early. The intermediate agreement requires a deed, a five year lease, or a purchase option. You cannot start the interconnection study without it.
- Build for curtailment. Any site that interconnects after December 31, 2025 must be able to reduce load or switch to backup generation when ERCOT commands. That means on-site backup generation and fuel supply contracts must be part of the design from the start.
- The queue is competitive and full of phantom projects. Many requests will never turn into real sites. A developer with firm financing, site control, and a complete application will move ahead of speculative filings.
- Co-location with an existing generator requires separate approval. Do not assume you can simply contract with an existing solar or gas plant without going through the PUCT review.
- Transmission buildout is on a longer track. The first 765-kV line is not expected until late 2028. Connection timing for a project in West Texas may depend on when the new high voltage backbone reaches the area.
- Watch the PUCT rulemaking. The proposed § 25.194 could change after the public comment period. The final rule will shape the financial terms and milestones for every project that enters the queue after its adoption.
Frequently asked questions
Q:What is the minimum size to trigger the ERCOT large load interconnection process?
A:
75 megawatts at a single site, measured at a common point of interconnection. The PUCT can lower that number. PURA § 37.0561, ERCOT Large Load Q&A
Q:How much financial security must an AI data center developer post?
A:
Under the proposed rule, $50,000 per MW in the intermediate agreement step, plus another $50,000 per MW non-refundable fee at the interconnection agreement step. Proposed § 25.194
Q:Can ERCOT force my AI data center to shut down?
A:
If the facility has on-site backup generating facilities (generation that cannot export to the ERCOT grid and in the aggregate can serve at least 50 percent of on-site demand), ERCOT can, after exhausting all available market services except frequency responsive services, direct the electric utility to require the facility to either curtail load or deploy its backup generation before or during an energy emergency alert. S.B. 6
Q:What if I withdraw my application?
A:
The security is split. The transmission service provider keeps 80 percent of the remaining security for its rate base. You get 20 percent back. Proposed § 25.194
Q:Can I avoid the full interconnection process by co-locating with an existing power plant?
A:
No. Any new large load over 75 MW that wants a net-metering arrangement with an existing generator must go through an ERCOT study and PUCT approval, unless it meets a narrow exemption. S.B. 6
Q:How many of the queued AI data center projects will actually get built?
A:
Only around 7.5 gigawatts of the queue had been connected or approved as of late 2025. Industry observers expect heavy attrition. CNBC
Q:Does Texas have enough generation to serve them all?
A:
Not yet. The current generation fleet can serve about 105 GW. The queue holds many times that, but turning those megawatts into real power plants takes years. ERCOT April 2026 Update
Q:How long will it take to get interconnected?
A:
The full process can take a year and a half or longer. ERCOT’s published interconnection process runs 18 to 30 months for large generation, and the volume of large load requests will likely extend timelines further. ERCOT interconnection process
Q:What is the Texas Energy Fund, and does it help AI data centers?
A:
The TEF is a $10 billion state fund that makes low-interest loans to build dispatchable generation inside ERCOT. Developers building gas plants have used TEF loans to reduce financing costs. PUCT TEF page
Q:Where can I find the latest rules and forms?
A:
The PUCT’s interchange page for Project 58481 has the proposed rule text, and ERCOT’s Large Load Working Group releases updates on the batch process. PUCT Project 58481, ERCOT Large Load Working Group
Subscribe to The Compute Law Brief
The Compute Law Brief is a free weekday newsletter on the law of AI infrastructure across tax, real estate, construction, power, and deals. The big US build markets and federal law. Three minutes a morning. No paywall, and no email gate to read the blog. Subscribe if you want it in your inbox.
Junde Liu, JD, LL.M. (Taxation) candidate at UF Law. Originally published on Compute Law Blog. This article is general information and does not constitute legal advice. Reading it does not create an attorney client relationship. The reader should not act on the basis of any content here without first consulting a licensed attorney in the relevant state. Last reviewed for accuracy May 23, 2026.